Nottingham Express Transit (NET) Phase II: Nottingham Tram Extension Scheme

lorem ipsum dolor sit

Demolition of Queens Medical Centre overhead link

Structure situated within the sensitive teaching hospital environment - works pre-planned for Sunday morning to minimise disturbance to patients, visitors and staff.

Hand separation, mechanical extraction and contract lift crane operations utilised in the safe demolition of the link bridge.

lorem ipsum dolor sit

Former Wilkinsons Store, Beeston Square, Nottingham

Structure situated within the Beeston Square Shopping Centre environment requiring specific protective measures to be installed including propping and separation works.

Mechanical demolition of 2 storey Wilkinson structure whilst maintaining integrity of neighbouring party wall

 

lorem ipsum dolor sit

Arkwright Street, Nottingham

Structure situated within Nottingham City Centre, close to Nottingham Train Station requiring specific public and traffic protection. Traffic plan agreed with Nottingham Highways.

Asbestos Removal, Soft-strip and mechanical demolition of traditional build mixed commercial and residential structures.

 

PROJECT SPECIFICS

Client

Vinci Construction Uk Limited

Building Type

80+ structures varying from steel framed; concrete – pre-stressed / insitu/encased; timber; traditional etc;

Project Summary

January 2012 - December 2014
The scheme consisted of the phased Demolition of 80+ structures varying from former private dwellings, industrial units, office, shopping complex and elderly persons and educational structures to enable commencement of Nottingham tram infrastructure

Project Value

£1.5m

PROJECT SCOPE

Following on from our successful Phase 1 works, we secured the Phase II Tram Extension scheme which saw the existing route from the M1 through to Nottingham City Centre extended from Nottingham City Centre, through the Meadows and out to Beeston town centre and also linking the main Nottingham Accident and Emergency Hospital. The scheme consisted of the phased Demolition of 80+ structures varying from former private dwellings, industrial units, office, shopping complex and elderly persons and educational structures to enable commencement of Nottingham tram infrastructure.

High-level Summary of Project

The overall scheme included:- Liaising with client representatives;

Weekly progress /planning meetings;

Preparation of RAMS specific to each site by in-house Demolition Engineer;

Arranging for refurb/demolition asbestos survey specific to each structure;

Arranging for disconnection of all services specific to each site;

Assignment of public protection measures specific to each site;

Asbestos removal phase to each specific site;

Demolition by mixture of hand/brokk (robotic) and mechanical (including high reach) specific to each site;

Nottingham City Highways to agree proposed traffic management and planning condition issues;

Installation of full public protection measures incl. full height demolition spec scaffold and crash decking etc;

Installation of designed raking props to party walls;

Asbestos removal;

Hand separation; Normal demolition rig and High reach demolition operations;

Dust containment –on-board suppression systems to excavator + supplementary bowser with spray mist attachment;

closed type ‘Heras’ fencing;

Water management;

Spillage controls

In Consultation With

Nottingham City Highways

Timescales

The programme of works was fully completed within 23 months.

 